EXTERIOR PHASES 1

Overall Exterior Ghantt Chart

Project Start: Mon, 2/17/2020
Display Week: 1 Feb 17, 2020 Feb 24, 2020 Mar 2, 2020 Mar 9, 2020 Mar 16, 2020 Mar 23, 2020 Mar 30, 2020 Apr 6, 2020
  17 18 19 20 21 22 23 24 25 26 27 28 29 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12
TASK ASSIGNED
TO
PROGRESS START END   DAYS M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S
Exterior Miscellaneous                                                                                                                            
Exterior signage designs completed   100% 3/13/20 3/13/20   1                                                                                                                
Signage designs approved (all exterior applications)   3/20/20 3/20/20   1                                                                                                                
Style Guide Complete      3/27/20 3/31/20   5                                                                                                                
Phase 1 Hospitals: GM/Woodbine                                                                                                                            
Site Survey   100% 3/16/20 3/20/20   5                                                                                                                
Drawings sent for Review/approval     4/10/20 4/10/20   1                                                                                                                
Approvals Received     4/15/20 4/15/20   1                                                                                                                
Manufacturing/Production     4/16/20 5/29/20   44                                                                                                                
Permitting/Exsisting sign upgrade/Installation   6/5/20 6/30/20   26